Renovation timeline planner · 2026

How long will your kitchen renovation actually take?

Replacing or reconfiguring a kitchen — from strip-out through first-fix services, plastering, unit and worktop fitting, tiling, appliance install and final snagging. Standard like-for-like fits land in 3–4 weeks on site; full reconfigures with structural work and stone worktops typically run 6–10 weeks.

Sources cited per phaseNo email gateUpdated quarterly
The plan

Kitchen Renovation

Replacing or reconfiguring a kitchen — from strip-out through first-fix services, plastering, unit and worktop fitting, tiling, appliance install and final snagging. Standard like-for-like fits land in 3–4 weeks on site; full reconfigures with structural work and stone worktops typically run 6–10 weeks.

Tell us about itLive updates — no submit button.
Scope
Reconfigure layout (no walls moved)
Kitchen size
Galley / compact (under 8 m²)
Worktop
Laminate (in stock)
Units
Trade (Howdens, Benchmarx)
Week-by-week

Your timeline

Hover any bar for the trade detail · scroll horizontally on small screens
Phase
W-15
W-14
W-13
W-12
W-11
W-10
W-9
W-8
W-7
W-6
W-5
W-4
W-3
W-2
W-1
DAY 1
W1
W2
W3
W4
W5
W6
Pre-construction · before day 1
Finalise design & order bespoke units
Order semi-bespoke kitchen (Wren/Magnet)
Architect / structural engineer drawings
Submit Building Notice or Full Plans
Order appliances
Order trade kitchen via fitter
Confirm RSJ / steel fabrication
Order tiles & splashback
Decant kitchen, set up temporary cooking
Confirm electrician, plumber, plasterer, tiler dates
On site · from day 1
Strip-out
First-fix plumbing
First-fix electrics
Plastering & floor prep
Floor finish
Base unit installation
Wall unit installation
Worktop template visit
Worktop fabrication (off-site)
Worktop fit
Splashback & tiling
Second-fix plumbing & appliances
Second-fix electrics
Decoration & snagging
On-site trade workRegulatory / professionalDecision deadline (you act)Contractor prep / lead time
On-site total
4.4–4.9 weeks

On-site only. Add ~14 weeks of pre-construction (planning, ordering, lead times) before day 1.

Reality check

Where it tends to slip

If your project goes long, it’ll usually be one of these. Worth knowing before you sign anything.

01Worktop template can only happen once base units are fixed and level — granite/quartz then needs 5–10 working days off-site, which is the single biggest schedule risk in a kitchen.
02Kitchen unit delivery slips — Wren/Magnet have reported 5–7 week stretches; bespoke ranges back-up around Christmas, Easter and the August school break.
03Discovering uneven floors, undeclared structural walls or old tiled adhesive on lift — adds 1–3 days latex/levelling.
04Appliance back-orders, especially boiling-water taps, integrated wine fridges and US/EU branded ovens.
05Tradesman gap — tiler waiting for the plumber, electrician booked elsewhere; clusters of small days lost between phases.